Special program 1 phase program - 2017

 

  Special program 1 phase program
             
No project G.N Divition Estimated cost (Rs.) Expenditure (Rs) No of                 Beneficiaries Name of Contraction
1 Atakohota rd in concrete 41 F Diyapetagallana     396,900.00      372,923.48 15 "Thalgaha watta"Rural development society 
2 Nagasgodalla kanada uda rd in concrete  41 D Siripura     475,300.00      469,760.55 20 "Shakthi "Rural development society 
3 Hodapaluwa  kapart rd in concrete 41 E Beligaswella     343,000.00      339,140.00 10 "Shakthi" samurdhi based organization

 

Special program 2 phase program - 2017

 

  Special program 2 phase program
             
No project G.N Divition Estimated cost (Rs.) Expenditure (Rs) No of                 Beneficiaries Name of Contraction
1 Siybalagaha junctuon to pahalamanana roada tara &concrete 91 B Randenigama  1,500,000.00  1,485,000.00 100 "Ranmini" samurdhi community based organization
2 totupala raod in unagaswela concrete 91 D U nagaswela  1,500,000.00  1,485,000.00 70 "Saruketha" Farmers society 
3 mara tree in magala south to akkara 24 margaya in tar 95 Magala south  1,500,000.00  1,485,000.00 40 "Siha shakthi" samurdhi community based organization
4 play ground of kiripedd school at kiripedda in tar &concrete 93 B Ihala kiripedda  1,500,000.00  1,485,000.00 100 "93 B Ihala kiripedda" samurdhi Community based organization
5 taring hodapaluwa dikhena road at kaluwalagoda 41 D Kluwalagoda  1,500,000.00  1,485,000.00 115 "Thisra samurdhi" samurdhi community based organization
6 near the mr.karunasena's house to karawa at dangahavila tar & concrete 91 C Dngahavila  1,500,000.00  1,485,000.00 100 "Dangahavila" Samurdhi community based organization
7 veemola in kolawela to naminigoga road in concrete 95 A agulugalla  1,500,000.00  1,485,000.00 300 "Vasana" samurdhi  community based organization
8 Beligaswella halgahawella sub road at uragasman handeya east-concrete 39 C U ragasmanhandiya east  1,500,000.00  1,485,000.00 500 "Shakthi"samurdhi community based organization
9  Recived sports goods G.N. Division In 32     500,000.00      499,850.00 32 (sports club)  

 

Decentralized Capital Budget Programme - 2017

No project G.N Divition Estimated cost (Rs.) Expenditure (Rs) No of                 Beneficiaries Name of Contractor
1 Construction  the Drain system  road  from Uragasmanhandiya Meegaspitiya Rd  to  Hirikumbura Rd. Meegaspitiya               200,000.00             193,890.00 Family30 Suhada  Agrerian Society  -Meegaspitiya.
2 Improvement of Bodhimaluwa by laying Decorative Interlocking concrete blocks , at Yatagala Sri Bodirajaramaya. Yatagala               200,000.00             193,297.30 Family 650  Dayaka Sabawa - Sri Bodirajaramaya  - Yatagala. 
3 Supply Electricity and development works in Mr.Wilson Wijethunga Playgruond at  Kurundugahahetekma. Kurundugahahetekma.               200,000.00             194,000.00 Family 200 Pubudu Rural Development Society - Kurundugahahetekma.  
4 Improvement  of  road by laying concreet Kekiriskanda road from Galagawala to Rathnakarawatta junction at Magala south and Pehembiyakanda G/N. Division. Magala South               200,000.00             189,524.75 Family 150 Navoda Rural Development Society - Pehembiyakanda.
5 Repairing works  of Toilets at Hipankanda K.V. Hipankanda               100,000.00               96,905.37 students  150 School Development Society -Hipankanda K.V.
6 Construction of Netball court in  Central College Karandeniya. Mahaedanda               200,000.00             193,931.93 students  3500 School Development Society -Karandeniya.M.M.V.
7 Development of the road, near the house of Mr.Jilman Korakeena.  Yatagala               250,000.00             242,486.05 Family 200 Perakum Agrerian Society - Yatagala .
8 Construction of the Dharma Shalawa  Iddaseehamanthindaramaya ,Mabingoda. Mabingoda               200,000.00             192,996.00 Family 342  Dayaka Sabawa -Iddaseehamanthindaramaya.
9 Place Iron grill cover to classroom in G/Magala Wipulasara maha Vidyalaya. Magala North               200,000.00             193,072.56 Students  415 School Development Society -Wipulasara maha Vidyalaya.

Provincial council Projict- 2017

No project G.N Divition Estimated cost (Rs.) Expenditure (Rs) No of                 Beneficiaries Name of Contraction
1 Aganakatiya Thalgahawatta kiripedda Road 93 Aganakatiya 970,000.00 969,904.88 1500 Aganakatiya samurdhi community based organization

News & Events

28
Aug2017
Karandeniya Divisional Coordinating Committee Meeting 2018

Karandeniya Divisional Coordinating Committee Meeting 2018

Karandeniya Divisional Coordinating Committee Meeting will be...

Scroll To Top